Qatar Refinery Junction Box Deployment

Published: 2026-06-08 · Last updated: 2026-06-08
Customer
XX Refinery (Qatar)
Oil refinery (downstream)
Location
Qatar, Middle East
Sector
Oil & Gas

Background

A downstream refinery in Qatar with 35,000 barrels per day capacity needed to replace aging junction boxes across its process units. The original equipment was reaching end-of-life and the refinery wanted to consolidate on a single supplier with ATEX/IECEx dual certification to simplify spare parts management.

Challenge

  • 6-week total shutdown window — no margin for delay
  • 220 junction boxes across 4 process units
  • Mix of Ex e IIC (increased safety) and Ex d IIC (flameproof) requirements
  • 316L stainless steel required for coastal salt-spray environment
  • Documentation package required for Qatar Civil Aviation / regulatory audit

Our Solution

  • Free application assessment: confirmed Zone 1, Gas Group IIC, T4 temperature class
  • Standard 316L Ex e IIC junction boxes in 8 standard sizes (matched to existing cable entries)
  • Custom laser-etched serial numbers and QR codes for traceability
  • Pre-tested with 100% hydrostatic test per IEC 60079-1
  • Pre-shipment documentation package: 12 documents including certificates, mill certs, and FPC audit reports

Implementation Timeline

  1. Week 0
    Quotation and technical review (2 business days from inquiry)
  2. Week 1-3
    Manufacturing in Xiamen factory. 100% batch testing. FPC audit.
  3. Week 4
    Sea freight to Doha (FOB Xiamen, CIF Hamad Port). 18 days door-to-door.
  4. Week 5
    Pre-shutdown staging at refinery. Engineering walk-down.
  5. Week 6
    Installation during scheduled 6-week shutdown. On-site engineer support.

Results

14+ months
Mean Time Between Failures (since commissioning)
100% (matched shutdown window)
On-time delivery
220/220 (100%)
Hydrostatic test pass rate
12/12 documents per shipment
Documentation completeness

Customer Voice

"The documentation package was the most complete we have seen from any supplier in this category. Our auditors had zero follow-up questions. We are evaluating the same equipment for two other units."

Project Engineer, XX Refinery (Qatar)

Products Deployed

Certifications

  • ATEX 2014/34/EU (Notified Body: TUV Rheinland)
  • IECEx (CoPC scheme)
  • ISO 9001:2015
  • EN 10204 3.1 (mill certificates)
How to cite this case study

Youngly Tech. (2026). Qatar Refinery Junction Box Deployment. Retrieved from https://younglytech.com/case-studies/qatar-refinery-junction-box/.